NATIONAL
The U.S. Army Corps of Engineers (USACE) is preparing to reissue and modify the existing 52 Nationwide Permits (NWPs). The proposal also includes the issuance of 5 new NWPs. The Notice of Proposed Rulemaking was posted to the USACE website on August 3, 2020, and is expected to be published in the Federal Register in a few weeks. Following publication in the Federal Register, a formal 60-day public comment period will commence. There are several key takeaways for InterAgency clients:
Potential Changes to Expiration Date:
The current NWPs were issued in 2017 (2017 NWPs) and are scheduled to expire in March 2022. The USACE is considering changing the expiration date of the 2017 NWPs to be the day before the proposed NWPs (2020 NWPs) take effect. If this happens, permittees would have at least 12 months to complete a previously authorized activity provided they are under construction, or under contract to construct, before the modified NWP takes effect.
Proposed New NWPs:
NWP A: Seaweed Mariculture Activities
NWP B: Finfish Mariculture Activities
NWP C: Electric Utility Line and Telecommunication Activities (currently under NWP #12)
NWP D: Utility Lines for Water and Other Substances (currently under NWP #12)
This would include potable water, sewage, wastewater, stormwater, etc.
NWP E: Water Reclamation and Reuse Facilities (currently under NWPs #29, 39, 40 and 42)
Proposed Revisions to NWP #12 (Utility Line Activities):
NWP #12 previously encompassed all utility line activities. As proposed, NWP #12 would be limited to only oil and natural gas pipelines, with other utility lines being covered under NWP C and NWP D. Note that the basic structure of NWP #12 would be retained for NWPs C and D.
The USACE is also considering significantly reducing the number of circumstances that would require an applicant to submit a pre-construction notification (PCN) for NWP #12, as well as NWPs C and D.
Waiving PCN Requirements for Federal Agencies:
To streamline the process for federal agencies, USACE is considering limiting the PCN requirements to non-federal applicants only.
Proposed Removal of the 300 Linear Foot Limit for Loss of Stream Bed:
Currently, NWPs #21, 29, 39, 40, 42, 43, 44, 50, 51, and 52 have a 300 linear foot limit for the loss of stream bed. The USACE is proposing to remove the linear foot limit and instead quantify stream impacts based on acreage. Thus, cumulative wetland and stream impacts would be calculated consistently to determine if the total impacts are less than the ½ acre limit for the relevant NWP.
Compensatory mitigation would now be required for losses of greater than 1/10 acre of stream bed that require a PCN.
The USACE is also considering a hybrid approach that would still quantify stream bed impacts in linear feet if there are no other impacts to wetlands.
Next steps:
Following publication in the Federal Register, each USACE District will issue a public notice requesting comments on proposed Regional Conditions for the NWPs and may also propose to revoke some of the NWPs within that District. Each USACE District will also coordinate with Certifying Authorities (i.e. states, authorized tribes and/or the US Environmental Protection Agency) regarding Clean Water Act Section 401 Water Quality Certification (WQC) for the NWPs. The Certifying Authorities will have 60 days to issue, deny or waive WQC.
InterAgency’s environmental permitting experts will continue to track developments carefully and assist clients in effectively navigating the federal environmental review process. To discuss in detail, please reach out to InterAgency’s Environmental Director, Doug Chapin, at doug.chapin@interagency.biz.